Project Resource Load
Calculate concurrent resource demand, capacity overload and total resource hours from task start and finish times. Tasks are not rescheduled automatically.
How resource loading works
Each row gives a task start, finish and constant resource demand. Enter all times in hours from the same origin. All rows must use the same resource type. Do not add workers and machines into a single total. Fractional demand can represent a divisible quantity such as full time equivalent staffing.
Concurrent demand
Start and finish events divide the schedule into intervals. Demand is summed across tasks active during each interval. The start is included and the finish is excluded, so a task ending at hour 2 does not overlap a task starting at hour 2. Two resources from hour 0 to 4 and three from hour 2 to 6 produce a peak of 5 and a total of 20 resource hours. With capacity 4, one resource is missing for two hours.
Limits
The tool does not assign resources or automatically level the schedule. You decide whether to move tasks. Average demand includes idle gaps between the first start and last finish. Overload duration adds the intervals above capacity. Missing resource hours sum the excess demand multiplied by its duration. Up to 200 tasks can be entered.
Separate total effort from simultaneous demand
Define three example tasks. The first needs 2 resources from 0 to 3 h, the second needs 1 resource from 1 to 4 h, and the third needs 3 resources from 4 to 6 h. Total demand is 2 × 3 + 1 × 3 + 3 × 2 = 15 resource hours. Across six hours, the average is 2.5 resources. With capacity set to 2, the average alone does not show the intervals with resource shortfalls. Demand is 3 from hour 1 to 3 and from hour 4 to 6. Total overload duration is 4 h and the resource hour shortfall is 4.
Check the effect of moving a task on total effort and peak demand separately. Moving only its start, without changing duration or demand, preserves total resource hours but can change overlap. Split a task whose demand changes during the day into intervals with constant demand. The capacity field is constant throughout the period. If shifts or leave change the number of available resources, this result alone is insufficient. Check separately that available resources have the skills needed for each task. Resource hours are neither monetary cost nor task calendar duration.
Related calculators
-
Civil Engineering
Critical Path Method (CPM) Calculator
Finds project duration, the critical path, early and late times and total and free float from an activity list with durations and predecessors, and draws a bar chart. -
Civil Engineering
Work Duration and Labour Hours Calculator
Finds total labour hours from quantity and hours per unit, then how many working days a crew needs or how many workers a target duration requires. -
Finance, Cost and Project Management
Material and Labour Cost Calculator
Builds a quote from material, labour and equipment lines with waste, overhead, profit and VAT, plus unit cost. Saved projects, CSV and print. -
Finance, Cost and Project Management
Bid Comparison Matrix
Compare two offers using your scores and weights for up to 20 criteria. -
Finance, Cost and Project Management
Break Even Calculator
Find sales volume needed to cover fixed costs or reach a target profit. -
Finance, Cost and Project Management
Calendar Project Schedule
Build a dated schedule and bar chart from working days, holidays and activity dependencies, with critical activities identified.
Found a mistake or something missing?
If a value looks wrong, a size is missing or you need a feature, write to us and we will fix it.