Excavation, Sloped Pit and Backfill Volume Calculator

Excavation volume of a vertical or sloped foundation pit and of a trench, with top dimensions, the extra volume caused by the slope and the backfill quantity.

Surplus cut is an approximate geometric difference. If backfill needs more bank material because of shrinkage, the surplus to haul decreases. No shrinkage ratio is calculated, so this is not a direct hauling quantity. Bottom dimensions in the prismoidal formula refer to the excavation base including working space.

How is excavation volume calculated?

A pit with vertical sides has a volume of bottom area times depth. If working space is left around the structure for formwork and waterproofing, it is added on both sides: the bottom becomes a + 2w by b + 2w.

Sloped excavation

Where the ground cannot stand vertically, the sides are cut to a slope. The slope is usually given as horizontal to vertical: at 1 to 1 the edge moves back one metre for every metre of depth. The top opening is wider than the bottom by m × h on each side.

The volume of this shape is slightly less than the average of the bottom and top areas times the depth. The prismoidal formula gives the exact value:

V = h / 6 × [a·b + (a + a′)·(b + b′) + a′·b′]

Averaging the two end areas counts the corners too generously.

Trench

A sloped trench has a trapezoidal section: V = (b + m × h) × h × L.

Example

A pit with a 10 m × 8 m bottom, 2 m deep with 1 to 1 slopes has a 14 m × 12 m top opening. The volume is 2 / 6 × (80 + 24 × 20 + 168) = 242.7 m³. Cut vertically it would be 160 m³, so the slopes add 82.7 m³.

Backfill

Backfill is the excavated volume less the volume of the structure left below ground. Apply the backfill shrinkage allowance separately to determine the surplus for hauling.

Limits

Results are bank volumes. Excavated soil swells, so apply a swell factor separately for truck counts. The tool does not suggest a slope angle. Excavation safety depends on the ground investigation and the safety rules.

Frequently asked questions

How many cubic metres is a foundation excavation?

A 10 × 8 m foundation with 0.5 m working space on each side and 2 m depth has a vertical excavation volume of 198 m³. This is in situ volume, so haulage needs a separate swell allowance. The calculation does not establish whether vertical excavation is safe or whether shoring is needed.

Calculate with these values

How much excavation is needed for a sloped foundation pit?

For a 10 × 8 m foundation with 0.5 m working space on each side, 2 m depth and horizontal to vertical slope ratio 1, the excavation volume is 288.7 m³. All sides have the same slope on level ground. The slope is an input, not a safety recommendation, and ground and groundwater conditions require separate assessment.

Calculate with these values

Related calculators

Found a mistake or something missing?

If a value looks wrong, a size is missing or you need a feature, write to us and we will fix it.

Send an email