Truck Trips Calculator
Number of truck trips from cut volume, swell and body capacity, with an optional payload check and the job duration from cycle time and fleet size.
How many truck trips?
In earthworks the volume taken from the drawings is the bank volume of undisturbed ground. Excavated soil swells and goes on the truck at a larger volume. So first find the loose volume, then divide by what one truck carries:
loose volume = bank volume × (1 + swell)
trips = loose volume / volume carried per trip (rounded up)
Limited by volume or by weight?
Two things limit a truck: the volume of the body and the payload. Light material fills the body. Heavy material such as wet clay, rock or sand reaches the payload before the body is full. If you enter the loose density and the payload, the calculator uses the smaller of the two and tells you which one governs.
Example
200 m³ bank volume at 25 percent swell is 250 m³ loose. With a 14 m³ body that is 250 / 14 = 17.9, so 18 trips. With a 40 minute cycle and 4 trucks the job takes 18 × 40 / 4 = 180 minutes, or 3 hours.
If the loose density is 1600 kg/m³ and the payload 20 tonnes, a truck can take at most 12.5 m³ per trip and the count becomes 20.
Limits
Swell depends on the soil and body capacity on the vehicle. Both are your inputs. The duration assumes uninterrupted work. In practice loader output, traffic, waiting at the tip and breakdowns govern. Check legal weight limits separately.
Related calculators
-
Civil Engineering
Excavation, Sloped Pit and Backfill Volume Calculator
Excavation volume of a vertical or sloped foundation pit and of a trench, with top dimensions, the extra volume caused by the slope and the backfill quantity. -
Civil Engineering
Soil Swell and Shrinkage Calculator
Convert between bank, loose and compacted soil volumes, find the cut needed for a fill, and derive swell and shrinkage percentages from densities. -
Civil Engineering
Bar Bending Schedule (BBS) Calculator
Cutting length, total length and weight per bar mark from diameter, shape and dimensions. Straight, L, U and stirrup shapes, bend deduction, CSV and print. -
Civil Engineering
Brick and Block Quantity Calculator
Number of bricks, concrete blocks or AAC blocks from wall and unit dimensions, with openings, joints, waste, units per square metre and joint mortar volume.
Found a mistake or something missing?
If a value looks wrong, a size is missing or you need a feature, write to us and we will fix it.